3rd St. project progressing
The Third Street south paving project is moving along. City Engineer John Zwingman, said it is on schedule. “So far it’s moving well. We have about a little more than onefourth of the block between Main and Elm done. We’ll be proceeding with another section of that this week. Sanitary sewer will be going in this week, and then next week we’ll proceed with storm sewer and water, beginning on the south end and working our way to the north,” he said. Zwingman was in Humphrey Sunday to check on the site, and said even Saturday’s rain did not hamper progress. “It sure didn’t hurt us. I drove up just to make sure. I would say the middle of August they will be done with the block near downtown,” he said. The target date for completion of the project is Sept. 15, of course, that depends on weather cooperating.